A
Acceleration
Adding resources, or changing the sequence or method, to finish the work sooner than it would otherwise finish.
The SCL Protocol's definition covers both achieving the planned scope of work in a shorter time than planned and fitting extra work into the original time. It is a kind of mitigation. It is not a cause of action: a claim for its cost needs a term of the contract or a breach. HHJ Hicks QC in Ascon asked the two questions that decide who pays: "earlier than what?" and by whose decision the relevant steps were taken.
Explained in 10. Acceleration · See also Mitigation, Constructive acceleration, Acceleration Quotation · Used at 6.3.2, 10, 11.1.6
Acceleration Quotation
The JCT 2016 procedure by which the employer invites a priced proposal for finishing before the Completion Date.
If the employer wishes to investigate completing before the Completion Date, the Architect/Contract Administrator (under Design and Build, the Employer) invites the contractor's proposals (SBC/Q 2016 Schedule 2; DB 2016 Supplemental Provision 4). The contractor is under no obligation to accelerate until its quotation is accepted by a Confirmed Acceptance. NEC4's equivalent is clause 36.
Explained in 10. Acceleration · See also Acceleration · Used at 10.2.2
Accepted Programme
Under NEC4, the programme identified in the Contract Data or the latest programme the Project Manager has accepted.
Explained in 2. The programme: critical path and float · See also Critical path · Used at 2.5.1, 6.4.8, 14.3.5, 16.4.2
Act of prevention
Anything the employer does, lawful or not, that actually delays completion beyond the completion date.
It need not be a breach. Actions by the employer which are perfectly legitimate under a construction contract may still be characterised as prevention, if those actions cause delay beyond the contractual completion date (Multiplex [56]), such as ordering extra work. It must cause real delay: the prevention principle necessarily means prevention in fact (Adyard [264]). Where the extension clause covers the act, the completion date moves and time is not set at large.
Explained in 3. Extensions of time · See also Prevention principle, Time at large, Extension of time · Used at 3.3.4
Adjudication
The statutory fast procedure for construction disputes: a decision within 28 days of referral, binding until a court, an arbitrator or agreement finally decides the dispute.
A party to a construction contract can refer a dispute under it to adjudication (Construction Act 1996, s.108). The adjudicator must reach a decision within 28 days of referral. That can be extended by up to 14 days with the referring party's consent, or longer if both parties agree (s.108(2)(c)-(d)), and the decision binds until the dispute is finally determined by legal proceedings, arbitration or agreement (s.108(3)). The courts enforce decisions unless the adjudicator answered the wrong question or acted in an obviously unfair way (Carillion [85]).
Explained in 15. Experts and the tribunal · See also Arbitration · Used at 1.5.6, 6.4.5, 7.6.8, 10.5.3, 14.5.8, 15, 16.3.7
Apportionment
Splitting a concurrent period of delay, or its cost, between the two causes.
Available in Scotland where two causes operate and neither is dominant: the decision-maker, approaching the issue in a fair and reasonable way, may apportion the delay. In England there is no general power to apportion responsibility for delay; the contractor gets a full extension for the concurrent period and no money. A contract can provide its own apportionment machinery, which must then be pleaded and used.
Explained in 8. Concurrency · See also Dominant cause, Concurrent delay, Concurrency clause · Used at 8.6.1, 12.5.6
Arbitration
A private process, used only if the parties agree to it, in which a tribunal they choose makes a final and binding award.
In England and Wales it is governed by the Arbitration Act 1996, as amended by the Arbitration Act 2025. The tribunal must act fairly and impartially as between the parties (s.33(1)(a)). The award is final and binding unless the parties agree otherwise (s.58(1)), subject to limited challenges in court (ss.67-69).
Explained in 15. Experts and the tribunal · See also Adjudication, Costs follow the event · Used at 1.5.7, 15.4.1, 16.6.1
As-built programme
A programme showing what was actually done and when, built from the progress records.
An as-built programme records actual start and finish dates rather than planned ones. It is often rebuilt after the event by a delay expert from the daily reports and other records. Under the TCC Guide, the part of an expert's evidence that establishes primary facts is to be treated as factual evidence.
Explained in 2. The programme: critical path and float · See also Critical path, Daily report · Used at 2.5.1, 6.3.2, 7.3.6, 14.5.7, 15.1.3
As-planned versus as-built windows analysis
Compares planned and actual dates along the critical path, window by window, with the path found from the facts rather than by software.
The second of the SCL Protocol's windows methods (SCL 11.6(d)). The analyst finds the critical path in each window by a common-sense and practical analysis of the available facts and must explain how criticality was decided. It needs only a baseline and as-built data.
Explained in 7. The six methods of delay analysis · See also Effect and cause analysis, As-built programme, Windows analysis · Used at 7.3.4
B
Back-to-back clause
A subcontract term that gives the subcontractor time for the events that give the main contractor time under the main contract.
It keeps the main contract and the subcontract in step, so the main contractor does not owe its subcontractor time it cannot recover from the employer. The subcontract in Steria gave time for any circumstance which entitles the contractor to an extension of time under the main contract (Steria [95]). Notice periods often differ between the two contracts, and that is where back-to-back arrangements tend to fail.
Explained in 3. Extensions of time · See also Extension of time, Prevention principle · Used at 3.6.3
Balance of probabilities
The civil standard of proof: the tribunal must find the fact more likely than not.
The standard for every fact in a delay claim. For loss and expense, the contractor has to demonstrate on a balance of probabilities the events, that they caused delay or disruption, and that the delay or disruption caused its loss (Walter Lilly [486(a)]).
Explained in 6. Proving delay: forecast or look back · See also Burden of proof, Loss and expense · Used at 6.5.1, 12.1.1
Baseline programme
The planned programme against which progress and delay are measured.
Usually the contractor's programme as first accepted by the certifier. In the SCL Protocol it becomes the Accepted Programme, which is then updated with actual progress. Delay is measured by comparing later versions, or the as-built record, with it.
Explained in 2. The programme: critical path and float · See also Accepted Programme, Updated Programme, As-built programme · Used at 2.5.1, 7.2.1, 15.5.4
Best endeavours (JCT)
The JCT proviso that the contractor must constantly use its best endeavours to prevent delay, however caused.
The Design and Build 2016 wording is that the contractor shall constantly use his best endeavours to prevent delay in the progress of the works, however caused (clause 2.25.6.1). The SCL Protocol says it may place a higher burden on the Contractor than the normal duty to mitigate. How far it requires the contractor to spend its own money is not settled.
Explained in 10. Acceleration · See also Mitigation, Acceleration · Used at 10.3.1
Broad axe
A tribunal's licence to estimate a loss that is proved but hard to measure. It does not prove the loss.
Where a loss has been proved but its amount cannot be measured exactly, a tribunal may make a sensible estimate rather than award nothing. The limit is that it does not relieve the Claimant of proving that a legally recoverable loss was suffered (Lumley Baxter v Aviva [124(v)], a County Court decision, persuasive only). In Cleveland Bridge the court assessed disruption at the minimum the evidence showed was probably caused.
Explained in 12. Global claims and causation · See also Global claim, Balance of probabilities · Used at 12.6.7
Burden of proof
The duty of a party to prove a fact it relies on; if it cannot, it loses on that point.
In a delay claim the contractor must prove that the events it relies on critically delayed it (Obrascon [272]); a party alleging that a notice was late must prove that ([313]). A tribunal need not always choose between the parties' cases. It may find that the party with the burden has failed to discharge that burden (Rhesa Shipping, as quoted in Citylink [64]).
Explained in 6. Proving delay: forecast or look back · See also Balance of probabilities · Used at 6.5.1, 7.6.7, 12.4.3, 15.1.5
But-for test
Would the loss have happened without this event? If it would, the event did not cause it.
The ordinary test of causation. It cannot answer concurrency on its own, because removing either cause leaves the job just as late. English law keeps it for money: unless the contract says otherwise, a contractor recovers loss and expense for delay only where it satisfies the but-for test, since it would have suffered exactly the same loss from its own delay.
Explained in 8. Concurrency · See also Concurrent delay, Effective cause · Used at 7.2.7, 8.1.5, 12.1.3
C
Cause and effect analysis
A delay analysis that starts from an event and works out its effect on completion.
In the SCL Protocol's words, these methods start with the identification and description of an event (a cause) and thereafter seek to establish its impact. Impacted as-planned, time impact analysis and collapsed as-built work this way. They measure only the events the analyst chooses to model.
Explained in 7. The six methods of delay analysis · See also Effect and cause analysis, Impacted as-planned analysis, Time impact analysis, Collapsed as-built analysis · Used at 6.2.6, 7.1.1
Certifier
The person who runs the contract and decides extensions of time and money claims; the contract may call this person the architect, contract administrator, employer's agent, project manager or engineer.
The SCL Protocol calls this person the contract administrator: the person responsible for administration of the contract, including certifying what extensions of time are due and what loss and expense is to be paid (App A). It may be one of the employer's employees, or the employer itself. The certifier has two functions. As agent it carries out the employer's wishes. When it decides between the parties its duty is to hold the balance fairly between employer and contractor (Scheldebouw [24], a case about a construction manager). It is not independent, but must act in an independent manner ([26]).
Explained in 5. The certifier · See also Extension of time · Used at 1.5.2, 2.5.1, 3.1.6, 4.1.6, 5, 7.1.2, 9, 10
Collapsed as-built analysis
Takes delay events out of a logic-linked as-built programme to estimate when the job would have finished without them. Also called but-for analysis.
One of the SCL Protocol's six methods (SCL 11.6(f)). The programme it needs is rare, so the analyst usually adds logic to the as-built record, and that logic is open to attack. It measures only incremental delay, because the finish will not collapse past the next near-critical path.
Explained in 7. The six methods of delay analysis · See also Cause and effect analysis, As-built programme, But-for test, Near-critical path · Used at 7.2.7
Compensation event
Under NEC4, an event listed in the contract that can change the Prices, the Completion Date or a Key Date.
The contractor must notify a compensation event within eight weeks of becoming aware that it has happened, unless it arises from the Project Manager's or Supervisor's own instruction or other communication (clause 61.3). The changes to Prices and dates are the parties' only rights in respect of a compensation event (clause 63.6).
Explained in 16. JCT, NEC and FIDIC compared · See also Early warning, Time bar · Used at 2.5.6, 3.2.5, 4.1.4, 6.4.8, 10.2.3, 11.3.2, 13.1.2, 15.5.9
Completion date
The date by which the contract requires the works to be complete, as moved by any extension of time.
Liquidated damages run from it. JCT and NEC4 call it the Completion Date; FIDIC works from the Time for Completion. An extension of time fixes a later completion date, so that liquidated damages run only from the new date.
Explained in 3. Extensions of time · See also Extension of time, Liquidated damages · Used at 2.4.4, 9
Concurrency clause
A contract term that says what happens to time, and sometimes money, when delays are concurrent.
Explained in 8. Concurrency · See also Concurrent delay, Apportionment · Used at 8.5.5, 9.6.7
Concurrent delay
One period of late completion with two effective causes of roughly equal weight, one at the employer's risk and one at the contractor's.
The working definition is John Marrin QC's, adopted by the Court of Appeal in North Midland, in a passage it called only tangentially relevant to the appeal: a period of project overrun which is caused by two or more effective causes of delay which are of approximately equal causative potency. Each cause must be driving the completion date; a delay that is not on the critical path cannot be a concurrent cause. In England the contractor gets time but not money for the concurrent period.
Explained in 8. Concurrency · See also True concurrency, Effective cause, Apportionment, Concurrency clause · Used at 1.3.5, 2.3.5, 6.2.4, 8, 9.6.6
Concurrent evidence
Opposing experts giving evidence together, questioned first by the judge and then by the parties' advocates; often called "hot-tubbing".
The court may direct that some or all of the evidence of experts from like disciplines shall be given concurrently (PD 35 11.1). The judge leads the discussion, then invites the parties' representatives to ask questions (11.4). The TCC Guide says the experts are generally cross-examined on general matters and key issues first (14.8.2).
Explained in 15. Experts and the tribunal · See also Joint statement, Delay expert · Used at 15.3.6
Condition precedent
A step that must be taken before a right arises; if it is not taken, the right is lost.
A notice clause is a condition precedent when it makes the right to time or money depend on the notice. The Court of Appeal's test in DBS v Tata is that the clause needs something that makes the relief conditional upon the requirement. Clear words will usually be needed, but the clause need not use the label. An "if ... then" or "provided that" structure is the usual sign.
Explained in 4. Notices and time bars · See also Time bar, Notice of Claim · Used at 3.6.4, 4, 9.3.7, 10.3.6, 13.1.6, 16.3.1
Constructive acceleration
Acceleration a contractor says it was forced into because an extension of time it was due was refused or granted late.
A United States concept. The SCL Protocol defines it and adds that it is rarely recognised under English law. The Protocol's advice is to take steps to have the dispute about the extension resolved first, and to give notice of the intended measures before spending money on them.
Explained in 10. Acceleration · See also Acceleration, Extension of time · Used at 10.5.1
Contemporaneous record
A document made at the time of the events it records, or immediately after.
A record written as the work goes on, not afterwards. The SCL Protocol says records of progress and delay must be generated contemporaneously as the works progress, and not afterwards. FIDIC's 2017 Red Book calls them "contemporary records" and defines them as records prepared or generated at the same time, or immediately after the event behind the claim. Courts generally treat them as more reliable than a witness's memory, though that is not a rule of law.
Explained in 14. Records and evidence · See also Daily report, Disclosure · Used at 14.1.8
Contract administrator (CA)
The SCL Protocol's name for the person who administers the contract and assesses extensions of time.
The SCL Delay and Disruption Protocol (2nd edn, 2017) uses "CA" throughout. The guide calls the same person the certifier.
Explained in 5. The certifier · See also Certifier · Used at 5.1.5
Contractor Risk Event
An event that, under the contract, is at the contractor's risk. It gives the contractor neither time nor money.
The SCL Protocol's term for an event or cause of delay or disruption which under the contract is at the risk and responsibility of the Contractor (Appendix A). Its opposite is an Employer Risk Event. Which side an event falls on depends on the contract actually signed, including its amendments.
Explained in 3. Extensions of time · See also Employer Risk Event, Culpable delay, Extension of time · Used at 3.2.3
Cost and Cost Plus Profit
FIDIC's two measures of delay money. Cost includes overheads but not profit; Cost Plus Profit adds a profit percentage.
Cost is all expenditure reasonably incurred (or to be incurred) by the Contractor, including overheads, but not profit (FIDIC 2017 Sub-Clause 1.1.19). Cost Plus Profit adds the percentage in the Contract Data, or 5% if none is stated (1.1.20). Each Sub-Clause that gives money says which of the two it gives. Variations are valued separately.
Explained in 16. JCT, NEC and FIDIC compared · See also Extension of time · Used at 16.2.5
Costs follow the event
The general rule that the losing party pays the winning party's legal costs.
In court, the general rule is that the unsuccessful party will be ordered to pay the costs of the successful party (CPR r.44.2(2)(a)), though the court may order otherwise and looks at the parties' conduct. An arbitral tribunal applies the same principle unless it is inappropriate (Arbitration Act 1996, s.61(2)). The rule is about legal costs, not damages.
Explained in 15. Experts and the tribunal · See also Arbitration, Non-party costs order · Used at 1.4.6, 15.6.6
Critical delay
Delay to an activity on the critical path, which extends the whole job unless the work is accelerated or re-sequenced.
Explained in 2. The programme: critical path and float · See also Critical path, Float, Delay · Used at 1.1.1, 2.2.1, 6.1.4
Critical path
The longest chain of dependent activities through the job; its length fixes the finish date.
The longest sequence of activities through a project network from start to finish, the sum of whose durations determines the overall project duration. There can be more than one. A delay to an activity on the critical path will, without acceleration or re-sequencing, delay completion; a delay to any other activity uses up float first.
Explained in 2. The programme: critical path and float · See also Float, Effective cause · Used at 1.1.3, 2, 3.1.2, 5.3.2, 6.1.1, 7, 8, 9.3.4
Critical path method (CPM)
The calculation rules, usually run by planning software, that find the critical path and work out float.
The SCL Protocol describes it as the technique that, through the use of calculation rules, determines the critical path and calculates float. The rules are a forward pass (earliest dates) and a backward pass (latest dates); the difference between them is float.
Explained in 2. The programme: critical path and float · See also Critical path, Total float · Used at 2.2.3
Culpable delay
Delay for which the contractor is responsible under the contract.
The SCL Protocol notes it as an expression sometimes used to describe what the Protocol calls Contractor Delay. An employer event arriving during culpable delay gets an extension only for the delay it actually causes, added to the existing completion date.
Explained in 3. Extensions of time · See also Net method, Extension of time · Used at 3.5.6, 8.2.13, 9.6.7, 10.6.2
Cumulative impact
The claim that many disruption events together cost more than the sum of their separate effects.
The SCL Protocol says particular care is needed because of the risks of a global claim, but the approach may be valid if all causes of disruption can genuinely be said to be the Employer's responsibility and their financial effects cannot practicably be separated.
Explained in 11. Disruption and lost productivity · See also Disruption · Used at 11.6.6
D
DAAB (Dispute Avoidance/Adjudication Board)
FIDIC's dispute board, which decides disputes before any arbitration.
Under FIDIC 2017 disputes shall be decided by a DAAB (Sub-Clause 21.1). Its decision binds the parties at once, even if one of them gives a Notice of Dissatisfaction. If no Notice of Dissatisfaction is given within 28 days, the decision becomes final and binding (21.4.3, 21.4.4). The DAAB is not an arbitral tribunal.
Explained in 16. JCT, NEC and FIDIC compared · See also Notice of Dissatisfaction (NOD), Arbitration · Used at 16.6.3
Daily report
The site's record of each day's weather, labour, plant, deliveries, work done and problems met. Many sites call it the site diary.
The main progress record on a project. The SCL Protocol suggests a daily report for each work area recording weather, labour, deliveries, adverse conditions, working hours, plant and the work under way (Appendix B 2.2(a)), and that it state facts only (1.12). A report that men or machines stood idle is a matter of fact that belongs in it.
Explained in 14. Records and evidence · See also Contemporaneous record · Used at 14.2.3
Defined Cost
The NEC name for the contractor's cost that the contract recognises, to which the Fee is added.
What counts depends on the main Option chosen. Under Options C, D and E it is the cost of the components in the Schedule of Cost Components less Disallowed Cost (NEC4 cl 11.2(24)); Options A and B use the Short Schedule of Cost Components, and Option F has its own definition. A compensation event is priced as its effect on Defined Cost plus the Fee, a percentage applied to Defined Cost (cl 11.2(10), 63.1).
Explained in 16. JCT, NEC and FIDIC compared · See also Compensation event, Dividing date · Used at 6.4.8, 16.2.12
Delay
Work taking longer than planned; in claims, usually delay to the completion of the works.
The SCL Protocol says that when it refers to delay it is concerned with time: work activities taking longer than planned. Its focus is largely on delay to the completion of the works, which it calls critical delay (Part A para 2). Work can run late without causing the contract completion date to be missed; the Protocol calls that delay to progress (App A). Delay is different from disruption, which is about lost productivity.
Explained in 1. Why projects run late · See also Critical delay, Disruption, Critical path · Used at 1.1.1
Delay analysis method
A structured way of using the programme and the records to show which events delayed completion, and by how much.
The SCL Protocol describes six methods in common use and lists other methods that may suit particular cases. No method is required by law. A tribunal asks whether the method fits the case and was properly applied (Thomas Barnes [109]-[110]).
Explained in 7. The six methods of delay analysis · See also Critical path, Cause and effect analysis, Effect and cause analysis · Used at 7
Delay damages
NEC4's and FIDIC's name for liquidated damages for late completion.
NEC4 provides for them in Option X7: the contractor pays them at the rate in the Contract Data for each day from the Completion Date until Completion, take-over or a termination certificate. FIDIC's 2017 Red Book calls them Delay Damages (Sub-Clause 8.8) and says they are the only damages due for late completion, except on termination for the contractor's default.
Explained in 9. Liquidated damages · See also Liquidated damages · Used at 9.1.3
Delay expert
An independent specialist who analyses the programme and the records to work out what delayed completion and by how long.
Also called a programming expert. The delay expert's duty is to help the tribunal, not the client (CPR r.35.3). The tribunal, not the expert, decides as a matter of fact what delayed the Works and for how long. The delay expert's periods of delay are what the quantum expert prices.
Explained in 15. Experts and the tribunal · See also Quantum expert, Joint statement, Native file · Used at 1.5.5, 15.1.1
Delay to completion
Delay that causes the contract completion date to be missed.
In common usage the phrase can mean delay to the contractor's planned finish or to the contract completion date. The SCL Protocol uses it for delay to a contract completion date, and that is the date extension clauses and liquidated damages look to.
Explained in 6. Proving delay: forecast or look back · See also Delay to progress, Critical path, Extension of time, Liquidated damages · Used at 6.1.3
Delay to progress
Delay to the contractor's work that does not cause the contract completion date to be missed.
The SCL Protocol's term for a delay that holds up the contractor's progress without causing a contract completion date not to be met. Work can run late without the job finishing late, usually because the delayed work had float. A delay to progress may still push back the contractor's own planned finish. On its own it gives no extension of time.
Explained in 6. Proving delay: forecast or look back · See also Delay to completion, Float, Critical path · Used at 6.1.3
Disclosure
The court process by which each party makes its relevant documents available to the other.
In the Business and Property Courts, which include the TCC, disclosure is governed by PD 57AD. A "document" includes any record of any description containing information, in any form, and extends to metadata. Electronic documents are provided in the documents' native format, in a manner which preserves metadata.
Explained in 14. Records and evidence · See also Known adverse document, Duty to preserve documents, Metadata · Used at 14.5.1
Disruption
Lost productivity. The work took more hours than it should have because something interfered with the contractor's planned way of working.
The SCL Protocol calls it a disturbance, hindrance or interruption to the contractor's normal working methods that lowers efficiency. It is about hours, not dates, so it can happen with or without delay to completion. It is not a cause of action by itself: the money has to come through the contract or a claim for breach.
Explained in 11. Disruption and lost productivity · See also Productivity, Measured mile, Loss and expense · Used at 1.1.6, 10.1.6, 11, 12, 13.4.1
Dividing date
The NEC date that splits a compensation event's assessment into actual cost before it and forecast cost after it.
For an event that arises from the Project Manager or the Supervisor giving an instruction or notification, issuing a certificate or changing an earlier decision, it is the date of that communication. For other compensation events, the dividing date is the date of the notification of the compensation event (NEC4 cl 63.1). Delay is measured against the Accepted Programme current at the dividing date (cl 63.5).
Explained in 16. JCT, NEC and FIDIC compared · See also Compensation event, Defined Cost, Accepted Programme · Used at 6.4.8, 16.2.12
Dominant cause
Where one of several causes clearly outweighs the others, the cause that decides the claim.
The test Scots law uses for delay claims (City Inn [42]; John Doyle [15], drawing on Leyland Shipping, a House of Lords insurance case). If a dominant cause can be identified, effect is given to it and the other causes are left out of account. Only where neither cause is dominant may a Scottish decision-maker apportion. English law does not use the test for loss and expense (Thomas Barnes [118]), and English courts have no general power to apportion (Tata v DBS [229]); a contract may provide its own machinery.
Explained in 8. Concurrency · See also Apportionment, Concurrent delay · Used at 8.6.3, 12.5.6
Duty to preserve documents
Once a party knows it may become a party to proceedings, it must keep relevant documents and stop routine deletion.
Under PD 57AD the duty arises for anyone who knows it is or may become a party to proceedings. It must take reasonable steps to preserve documents in its control that may be relevant, including documents a retention policy would otherwise delete, and must suspend relevant document deletion or destruction processes. Sometimes called a litigation hold.
Explained in 14. Records and evidence · See also Disclosure, Known adverse document · Used at 14.5.3
E
Early warning
Under NEC4, a notice by either side of a matter that could increase cost, delay completion or impair performance.
The Contractor and the Project Manager give an early warning by notifying the other as soon as either becomes aware of such a matter (clause 15.1). If the contractor fails to give one it should have given, the compensation event is assessed as if it had been given (clause 63.7).
Explained in 16. JCT, NEC and FIDIC compared · See also Compensation event · Used at 4.1.4, 16.5.4
Earned value
Comparing the hours the tender allowed for the work done with the hours actually spent.
The SCL Protocol describes it as comparing the amount of man-hours reasonably included in the tender allowance with the actual hours for the same work. It is simple, but it assumes the tender was achievable, and the Protocol warns that tender assumptions are not automatically a realistic baseline.
Explained in 11. Disruption and lost productivity · See also Measured mile, Productivity · Used at 11.4.3
Effect and cause analysis
A delay analysis that starts from the critical delay and then looks for what caused it.
These methods start with identifying critical delay (an effect) and thereafter seek to establish what might have caused that delay. Time slice windows, as-planned versus as-built windows and retrospective longest path work this way. After completion the Protocol regards them as generally more forensically reliable, because they consider every potential cause.
Explained in 7. The six methods of delay analysis · See also Cause and effect analysis, Time slice windows analysis, As-planned versus as-built windows analysis, Retrospective longest path analysis · Used at 6.2.6, 7.1.1
Effective cause
A cause that in fact delays completion, rather than one that is merely present while the job runs late.
Explained in 8. Concurrency · See also Concurrent delay, But-for test, Critical path · Used at 8.1.6
Eichleay formula
Allocates actual head office costs to the contract by its share of revenue, turns them into a daily rate, and multiplies by the days of compensable delay.
The SCL Protocol sets out three steps. The last is to multiply the figure resulting from Step 2 by the number of days compensable delay. The Protocol prefers it, with Emden, and suggests cross-checking one formula against another.
Explained in 13. The money · See also Hudson formula, Emden formula, Head office overheads · Used at 13.5.5
Emden formula
The Hudson calculation, but using the contractor's actual head office overhead and profit percentage.
The percentage is the contractor's head office overheads and profit percentage (actual), taken from its accounts rather than its tender. The SCL Protocol prefers it, with Eichleay, where a formula is used at all.
Explained in 13. The money · See also Hudson formula, Eichleay formula, Head office overheads · Used at 13.5.5
Employer Risk Event
An event that, under the contract, is at the employer's risk; its opposite is a Contractor Risk Event.
The SCL Protocol's term for an event or cause of delay or disruption which under the contract is at the risk and responsibility of the Employer (App A). A Contractor Risk Event is the same for the contractor. Which side an event falls on depends on the contract signed. An Employer Risk Event may give the contractor time, money or both.
Explained in 3. Extensions of time · See also Extension of time, Loss and expense · Used at 1.2.3, 2.4.5, 3.2.3, 9.3.4
Employer's Agent
Under JCT Design and Build, the person with authority to act for the Employer, who usually makes the Employer's extension decisions.
JCT Design and Build 2016 makes the Employer itself the decision-maker on extensions (cl 2.25.1). Article 3 gives the Employer's Agent full authority to act for the Employer under the conditions unless the Employer gives notice otherwise, so in practice the agent usually decides.
Explained in 5. The certifier · See also Certifier · Used at 5, 6.4.5
Estoppel
A rule that stops a party going back on a clear representation or shared assumption that the other party relied on to its detriment.
In Tata v DBS both parties had proceeded on precisely the same assumption that a five-day notice requirement had fallen away. The assumption was communicated and relied on, so the employer could not rely on the missed notice ([148], [159]-[163]).
Explained in 4. Notices and time bars · See also Waiver, Condition precedent · Used at 4.5.4
Extension of time
More time to finish, granted under the contract for events at the employer's risk, which moves the date from which liquidated damages run.
Explained in 3. Extensions of time · See also Liquidated damages, Net method, Prevention principle · Used at 1.1.2, 2, 3, 5, 6.1.2, 7.1.2, 8, 9
L
Learning curve
The slower output while a gang learns a new task or site. It is nobody's fault, so it must be kept out of a measured mile.
Explained in 11. Disruption and lost productivity · See also Measured mile, Disruption · Used at 11.5.2
Least disrupted period
The stretch of the job used as the measured mile when no part of it was free of disruption. It shows the minimum likely loss.
Where no clean period exists, the SCL Protocol suggests using a period of least disruption as the measured mile. The result is conservative, because it cannot capture the loss already inside the chosen period.
Explained in 11. Disruption and lost productivity · See also Measured mile · Used at 11.5.4
Legitimate interest
The innocent party's interest in the other side's performance, which a clause triggered by breach may properly protect.
Part of the penalty test in Cavendish v Makdessi. For a straightforward damages clause, such as an LD clause, the interest will rarely extend beyond compensation for the breach.
Explained in 9. Liquidated damages · See also Penalty · Used at 9.2.1
Liquidated damages
A sum fixed in the contract, usually per day or week, that the contractor pays for finishing late.
Agreed in advance, so the employer need not prove its loss. They run from the completion date as extended, which is why an extension of time for concurrent delay costs the employer its damages for that period.
Explained in 9. Liquidated damages · See also Extension of time · Used at 1.2.6, 2.4.2, 3, 4.2.6, 5.3.3, 6.1.6, 8, 9
Logic link
A rule tying one activity to another, most often "B cannot start until A finishes".
The ordinary link is finish-to-start: activity B cannot start until activity A has finished. Start-to-start and finish-to-finish links also exist, and any link can carry a lag, a required wait such as the curing time of concrete.
Explained in 2. The programme: critical path and float · See also Programme, Critical path · Used at 2.1.2, 15.5.4
Loss and expense
The JCT name for the money a contractor recovers under the contract for delay or disruption caused by employer-risk events.
Recovered under the contract's own machinery rather than as damages, but proved the same way: event, causation and loss. Unless the contract says otherwise, the contractor recovers nothing for a period of concurrent delay, because it would have suffered exactly the same loss from its own delay.
Explained in 13. The money · See also But-for test, Concurrent delay · Used at 1.3.3, 4.4.4, 5.1.1, 6.5.2, 8.2.5, 11.3.2, 12, 13.1.2
N
Native file
A file in the form the software that made it uses (for example a Primavera or Microsoft Project programme), rather than a PDF or print of it.
PD 57AD defines native format as the original form in which it was created by a computer software program. For a programme, the native file holds the logic links, durations, calendars, constraints and progress from which the dates, float and critical path are calculated. A PDF shows only the resulting bars. The SCL Protocol asks for the programme in native form, not just as a PDF.
Explained in 14. Records and evidence · See also Metadata, Disclosure, Critical path · Used at 2.1.3, 14.3.1, 15.3.5
Natural justice
The rules that a judge or arbitrator must hear both sides and be free of bias. They do not bind a certifier.
The Court of Appeal held in Amec that the rules of natural justice bind judges and arbitrators but not an Engineer giving a decision under the ICE conditions. A certifier must still act fairly: honestly, with skill and without favouring the employer.
Explained in 5. The certifier · See also Certifier · Used at 5.2.2, 15.5.1
Near-critical path
A chain of activities with so little float that a modest delay would make it critical.
The SCL Protocol uses the phrase without defining it. AACE says the purpose of quantifying near-critical paths is to reduce the effort of identifying and analyzing potential concurrent delays, and offers four criteria for choosing a threshold. Whether experts should rely on them is contested: in Santos v Fluor (Queensland, 2025) referees were entitled to reject an expert's reliance on them under an agreed method that did not call for them.
Explained in 2. The programme: critical path and float · See also Critical path, Concurrent delay · Used at 2.3.5, 7.2.9
Negative float
The amount by which a chain of activities must be shortened to meet a fixed date. It is the programme's way of showing delay.
The SCL Protocol notes that negative float only occurs when an activity on the critical path is behind programme. Once float goes negative, the critical path is the chain with the lowest float value, not the one showing zero.
Explained in 2. The programme: critical path and float · See also Total float, Critical path · Used at 2.2.5
Net method
Any extension for an employer event is added to the existing completion date, not measured from the date of the event.
The approach the court adopted in Balfour Beatty v Chestermount, as described in Walter Lilly: the "net" method was correct. The SCL Protocol says the same: any extension should simply be added to the contract completion date.
Explained in 3. Extensions of time · See also Extension of time, Culpable delay · Used at 3.5.7, 8.3.7, 10.6.2
Non-Completion Notice
The JCT notice the employer must issue when the contractor fails to complete by the Completion Date, before it can recover liquidated damages.
Under JCT Design and Build 2016, if the contractor fails to complete the Works or a Section by the relevant Completion Date the employer must issue one (cl 2.28). A new Completion Date fixed later cancels it, and a further notice is needed. It is the first of the notices the employer gives before recovering LDs.
Explained in 9. Liquidated damages · See also Pay Less Notice, Liquidated damages · Used at 9.3.5
Non-party costs order
An order that someone who was not a party, typically a person who funded and controlled a failed claim, pays the winner's costs.
The power comes from the court's full power to determine by whom and to what extent the costs are to be paid (Senior Courts Act 1981, s.51(3)). In Thomas Barnes (costs) (2026) the family who funded a failed claim were ordered to pay the Council's outstanding costs, jointly and severally.
Explained in 15. Experts and the tribunal · See also Costs follow the event · Used at 1.4.6, 15.6.7
Notice of Claim
Under FIDIC 2017, the first notice of a claim for time or money, due within 28 days of awareness.
Either party gives it as soon as practicable, and no later than 28 days after it became aware, or should have become aware, of the event or circumstance (Sub-Clause 20.2.1). A fully detailed claim follows within 84 days. A late Notice of Claim bars the claim, subject to the Engineer's 14-day response and the review of late notices in Sub-Clause 20.2.5.
Explained in 4. Notices and time bars · See also Time bar, Condition precedent · Used at 4.6.2, 16.3.3
Notice of Dissatisfaction (NOD)
Under FIDIC 2017, the notice a party must give within 28 days to stop the Engineer's determination becoming final and binding.
Under the FIDIC Red Book 2017, if no NOD is given within 28 days of the Engineer's determination, the determination shall be deemed to have been accepted by both Parties and becomes final and binding (Sub-Clause 3.7.5).
Explained in 5. The certifier · See also Certifier · Used at 5.6.9, 16.6.3
P
Pacing
Deliberately slowing non-critical work because the other side's delay has already pushed completion back.
Explained in 8. Concurrency · See also Concurrent delay, Float · Used at 2.4.12, 8.3.9, 10.1.7
Partial possession
The employer taking over part of the works before the whole is complete; the liquidated damages rate usually falls in proportion.
JCT reduces the rate by the same proportion as the value of the Relevant Part bears to the Contract Sum (cl 2.34). NEC4 reduces it by the Project Manager's assessment of the benefit to the Client of the part taken over (X7.3). FIDIC reduces the daily rate by value but leaves the maximum unchanged (Sub-Clause 10.2).
Explained in 9. Liquidated damages · See also Sectional completion, Liquidated damages · Used at 9.4.1
Pay Less Notice
The notice a payer must give under a construction contract before paying less than the sum otherwise due, for example to deduct liquidated damages.
The Construction Act 1996 lets the payer give a notice of the payer's intention to pay less than the notified sum (s.111(3)). JCT Design and Build 2016 reminds the employer that it needs one to withhold or deduct liquidated damages.
Explained in 9. Liquidated damages · See also Non-Completion Notice, Liquidated damages · Used at 9.3.5
Penalty
A clause triggered by breach that imposes a detriment out of all proportion to the innocent party's legitimate interest; a court will not enforce it.
The Supreme Court restated the test in Cavendish v Makdessi (2015): the question is whether the provision imposes a detriment out of all proportion to any legitimate interest of the innocent party. For a clause fixing damages, Lord Hodge's yardstick is the highest loss that could possibly arise. Between properly advised parties, the court starts from a strong presumption that a negotiated clause is valid. The name the contract gives the sum does not decide the point.
Explained in 9. Liquidated damages · See also Liquidated damages, Legitimate interest · Used at 9.2.1
Planned completion
The date on the contractor's programme when it plans to finish, which may be earlier than the contract completion date.
The SCL Protocol defines the contractor's planned completion date as the date shown on the Contractor's programme as the date it plans to complete. It warns that contractors sometimes call this the "completion date", and uses contract completion date for the contractual date to avoid confusion. NEC4 measures delay from a compensation event by how far planned Completion moves (cl 63.5).
Explained in 2. The programme: critical path and float · See also Project float, Total float · Used at 2.4.4, 16.4.2
Practical completion
JCT's end point for the works, when liquidated damages stop: the works are complete free from patent defects other than trifling ones.
JCT does not define it. The Court of Appeal in Mears v Costplan (2019) said it is easier to recognise than define, and summarised it as a state in which the works have been completed free from patent defects, other than ones to be ignored as trifling. Latent defects do not prevent it. NEC4's equivalent is Completion; FIDIC's is taking-over.
Explained in 9. Liquidated damages · See also Liquidated damages, Completion date · Used at 6.4.3, 9.3.2
Preliminaries
The contractor's site-wide costs of running the job, such as site staff, accommodation, plant and welfare, as opposed to the cost of the permanent work.
Many preliminaries are time-related, so they grow when the job runs late; this is the usual core of a prolongation claim. They can also be thickened, where more staff or resources are needed during a period rather than the same resources for longer. In Walter Lilly the court held that a claim for thickened preliminaries, linked to events and costed from the contractor's records, was not "total" or "global" ([491]).
Explained in 13. The money · See also Loss and expense, Prolongation · Used at 12.4.7
Prevention principle
An employer cannot hold the contractor to a completion date the employer itself has stopped the contractor meeting.
Where the contract has a working extension of time clause, the principle is not engaged: time is not set at large because the contract provides for an extension on the occurrence of those events. In what Coulson LJ called perhaps the most important reason of all, the Court of Appeal said that nothing in the authorities suggests parties cannot contract out of some or all of its effects. Its relationship with concurrent delay is open at appeal level.
Explained in 3. Extensions of time · See also Extension of time, Concurrent delay · Used at 1.2.7, 3, 4.5.1, 6.1.2, 8.1.2, 9.1.4, 10.6.4, 16
Productivity
Output for each hour of input, such as panels fixed per labour hour. Production is output alone.
A gang can hit its planned production and still lose productivity, by using more hours to do it. AACE's example is a pipe crew accomplishing 100% of planned production but operating at 50% productivity. Lost productivity is the difference between the productivity the contractor would realistically have achieved and what it actually achieved.
Explained in 11. Disruption and lost productivity · See also Disruption, Measured mile · Used at 11
Programme
The contractor's plan of the order and timing of the work, updated as the job goes on.
The SCL Protocol wants the contractor to prepare, and the certifier to accept, a programme showing the manner and sequence of the works, updated for progress, variations and extensions. It can then be used as a tool for managing change and deciding extensions (Core Principle 1). It should be kept in its native electronic form, and no version should be overwritten (1.43, 1.59).
Explained in 2. The programme: critical path and float · See also Critical path, Float · Used at 1.1.4, 2.1.1
Project float
The gap between the contractor's planned finish and the contract completion date. Also called terminal float.
AACE's term. Its recommended practice treats project float, absent contrary contract terms, as owned solely by the contractor. That is US practice. In England the wording of the extension of time clause usually decides who has the benefit of it.
Explained in 2. The programme: critical path and float · See also Total float, Planned completion · Used at 2.2.6
Prolongation
The extra period during which the contractor incurs time-related costs because of delay.
The SCL Protocol defines it as the extended duration of the works during which time-related costs are incurred as a result of a delay (App A). Prolongation costs are the costs of keeping the site and its staff running for longer. Whether the contractor recovers them depends on the contract and on proof that the employer's event caused them.
Explained in 13. The money · See also Loss and expense, Extension of time · Used at 1.2.8, 10.2.6, 11.1.7, 13
Prospective analysis
A forecast of an event's likely effect on completion, made on the information available at the time.
The SCL Protocol says a prospective delay analysis identifies the likely impact of historical progress or delay events on a completion date (11.4(e)). It is the natural frame for an extension of time decided during the works, such as the JCT interim decision. Its answer may differ from what later happened, because the contractor may accelerate or re-sequence the work.
Explained in 6. Proving delay: forecast or look back · See also Retrospective analysis, Extension of time · Used at 6.3.1, 7.2.6
R
Reasonable time
What replaces the fixed completion date when time is at large; judged objectively when the question arises.
The employer alleging the breach must prove what a reasonable time was, leaving out delays the contractor caused. In Shawton v DGP (2005) the Court of Appeal said it has to be judged as at the time when the question arises, in the light of all relevant circumstances.
Explained in 3. Extensions of time · See also Time at large · Used at 3.3.2, 9.6.1
Relevant Event
The JCT term for an event that entitles the contractor to an extension of time.
Listed in the JCT forms (for example clause 2.26 of the Design and Build Contract 2016). Some Relevant Events, such as variations, also carry money; others, such as bad weather, carry time only. NEC calls the equivalent a compensation event; FIDIC lists causes of delay in Sub-Clause 8.5.
Explained in 16. JCT, NEC and FIDIC compared · See also Extension of time · Used at 3.2.4, 4.4.6, 5.3.2, 6.4.4, 8.2.3, 15.5.2, 16.2.2
Relevant Matter
The JCT term for an event that entitles the contractor to loss and expense.
Listed in clause 4.21 of the JCT Design and Build Contract 2016. The list is not the same as the list of Relevant Events, which give time: some events, such as bad weather, give time but no money.
Explained in 16. JCT, NEC and FIDIC compared · See also Loss and expense, Relevant Event · Used at 3.2.4, 11.3.2, 13.1.2, 16.2.2
Relevant Omission
Under JCT, an instruction taking work out of the contract. It is the only ground on which a review may fix an earlier Completion Date.
On the end-of-job review under JCT Design and Build 2016, the Employer may fix an earlier Completion Date only having regard to any instructions for Relevant Omissions (cl 2.25.5.2). Otherwise an extension once granted stays.
Explained in 5. The certifier · See also Extension of time, Relevant Event · Used at 5.6.2, 16.3.6
Request for information (RFI)
A contractor's written question to the designer or certifier, usually asking for missing or unclear information, and the answer to it.
A dated log of requests for information shows when the contractor asked for each piece of information and when it arrived. The SCL Protocol lists requests for information and responses among the correspondence records to keep (1.31).
Explained in 14. Records and evidence · See also Daily report · Used at 14.2.6
Retrospective analysis
An assessment of an event's actual effect on completion, made after the event with the benefit of hindsight.
The SCL Protocol says a retrospective delay analysis identifies the actual impact of the delay events on the identified actual or as-built critical path (11.4(e)). Courts assessing damages use it, and the JCT final review after practical completion is one. It still has to trace what critically delayed the works as they went along, not blame the last event for the whole overrun.
Explained in 6. Proving delay: forecast or look back · See also Prospective analysis, Critical path · Used at 6.3.1
Retrospective longest path analysis
Traces the as-built critical path backwards from actual completion and compares its dates with the plan.
Explained in 7. The six methods of delay analysis · See also Effect and cause analysis, As-built programme, Critical path · Used at 7.3.6
S
Scheme for Construction Contracts
The default adjudication rules that apply where a construction contract does not meet the Construction Act's requirements.
If a contract does not comply with the Act's adjudication requirements, the adjudication provisions of the Scheme for Construction Contracts apply (s.108(5)). The Scheme is a statutory instrument (SI 1998/649). Its provisions take effect as implied terms of the contract (s.114(4)).
Explained in 15. Experts and the tribunal · See also Adjudication · Used at 15.4.2
SCL Protocol
The Society of Construction Law's Delay and Disruption Protocol (2nd edition, 2017): guidance on delay and disruption, not law.
The industry's standard guidance on programmes, extensions of time, delay analysis and the valuation of delay and disruption. It is not a contract document and does not state the law: it gives way to the contract and governing law (Introduction, para B). The first edition was published in 2002.
Explained in 1. Why projects run late · See also Delay, Disruption, Critical path · Used at 1.1.1, 15.2.7
Sectional completion
Separate completion dates, and usually separate liquidated damages rates, for defined parts of the works.
Used where the employer needs parts of a project before the whole, such as the first block of a school. The machinery has to work: some older clauses that tried to reduce one rate across parts could not be operated and failed.
Explained in 9. Liquidated damages · See also Partial possession, Liquidated damages · Used at 9.4.1
Stacking of trades
Several trades working in the same area at once and getting in each other's way.
One of the knock-on effects of disruption the SCL Protocol lists, alongside crowding of labour, dilution of supervision through fragmented work gangs, excessive overtime, repeated learning cycles and poor morale. It usually follows late or piecemeal access, out-of-sequence work or acceleration.
Explained in 11. Disruption and lost productivity · See also Disruption · Used at 11.2.2
Sub-network (fragnet)
A small, logically linked group of activities representing the work an event adds, inserted into a programme to model its effect.
The SCL Protocol calls it a sub-network: a group of activities or durations, logically linked, used to show the work flowing from an Employer Risk Event. "Fragnet" (fragment network) is the common trade name.
Explained in 7. The six methods of delay analysis · See also Impacted as-planned analysis, Time impact analysis · Used at 7.2.3
T
Task-related cost
A cost that rises and falls with the work and with how productively it is done.
Labour, productive plant and fuel are the usual examples. Disruption money is made mainly of these costs. Like "time-related cost", it is a working label used in this guide, not the SCL Protocol's own term.
Explained in 13. The money · See also Time-related cost, Disruption · Used at 13.2.2
Thickening
Extra site resources put on because of an event, as opposed to the same resources kept on for longer.
In Walter Lilly Akenhead J held that a claim for thickened preliminaries is not a global claim. Once the link between the event and the extra resource is proved, the costing of it is established by showing how many man weeks were consequently needed, multiplied by the salary cost ([491]).
Explained in 13. The money · See also Prolongation · Used at 13.3.7
Time at large
The fixed completion date falls away, and the contractor must finish within a reasonable time instead.
When time is at large, the obligation to complete by a fixed date is replaced with an implied obligation to complete within a reasonable time, and liquidated damages cannot run. The usual cause is an act of prevention by the employer for which the contract gives no extension. English first-instance decisions hold that a contractor's own failure to give a notice does not set time at large.
Explained in 3. Extensions of time · See also Prevention principle, Liquidated damages · Used at 3.4.5, 4.5.1, 9.6.1, 10.6.4
Time bar
A clause that removes a claim if notice is not given within a set period.
A time bar enforces a notice requirement that is a condition precedent. FIDIC 2017 Sub-Clause 20.2.1 (28 days) and NEC4 clause 61.3 (eight weeks) are the standard examples. A bar removes only what its words reach: it may take away money but leave the extension, or leave the contractor free to defend itself against the employer's delay claim.
Explained in 4. Notices and time bars · See also Condition precedent, Notice of Claim · Used at 4
Time impact analysis
Inserts an event into the updated programme current when it arose and recalculates; the change in forecast completion is the delay.
The method the SCL Protocol recommends for a contemporaneous analysis of delay, described at SCL 4.12 and 11.6(b). Because it forecasts, it usually does not capture the eventual actual delay. Often shortened to TIA.
Explained in 7. The six methods of delay analysis · See also Cause and effect analysis, Updated Programme, Sub-network (fragnet) · Used at 6.3.1, 7.2.5
Time risk allowance
Extra time a contractor builds into its programme for risks it carries itself.
The SCL Protocol's glossary describes it as additional time included by the Contractor within the allocated duration for an activity to allow for risks that are its own responsibility. The Protocol's guidance also accepts contingency shown as separate activities, and says either is perfectly acceptable and prudent planning practice. Allowance inside a duration does not show up as float.
Explained in 2. The programme: critical path and float · See also Total float, Float · Used at 2.2.8
Time slice windows analysis
Measures the critical delay in each period from a series of verified updated programmes, usually monthly, then looks for its causes.
The first of the SCL Protocol's two windows methods (SCL 11.6(c)). The series of updates reveals the contemporaneous or actual critical path in each time slice period. It is only as reliable as the updates it uses.
Explained in 7. The six methods of delay analysis · See also Effect and cause analysis, Updated Programme, Windows analysis · Used at 6.5.4, 7.3.2
Time-related cost
A cost that runs for as long as the site is open, whatever work is being done.
Site managers, cabins, security and welfare are the usual examples. Prolongation money is made mainly of these costs. The label is a working tool used in this guide; the SCL Protocol itself classifies costs as direct and indirect.
Explained in 13. The money · See also Task-related cost, Prolongation · Used at 13.2.2
Total cost claim
A global claim measured as the whole cost of the job less what the employer paid.
The American name for the commonest form of global claim. The contractor takes its total cost on the job, subtracts the payment it received, and attributes the balance to the employer's events by inference. Akenhead J said in Walter Lilly that "global" and "total cost" are not terms of art, and that there is nothing in principle wrong with such a claim. The contractor must still show the loss would not have been incurred anyway.
Explained in 12. Global claims and causation · See also Global claim, Modified total cost claim · Used at 12.3.1
Total float
How far an activity can slip without delaying the end of the job.
The SCL Protocol measures it to the contract completion date: the amount of time that an activity may be delayed beyond its early start/early finish dates without delaying the contract completion date. Planning software usually measures it to the programme's own planned finish, so check which date a float figure uses. Total float is shared along a chain of activities. It is also called slack.
Explained in 2. The programme: critical path and float · See also Free float, Project float, Float · Used at 2.2.6
True concurrency
Two delaying events, one at each party's risk, that happen at the same time and take effect at the same time.
The SCL Protocol's term for the strict case: two or more delay events at the same time, one an Employer Risk Event and one a Contractor Risk Event, whose effects are felt at the same time. The Protocol says it will be a rare occurrence. The more common usage covers events that arise at different times but whose effects are felt together.
Explained in 8. Concurrency · See also Concurrent delay, Effective cause · Used at 8.1.6